AKKUYU NUCLEAR POWER PLANT

Water intake and outfall lines; method design and installation works. 


Involves rock installation and levelling of 180,000 m2 area between 25 to 47 m depths to at 10 cm precision.  


Involves 1440 meters of 132 culvert units (intake line) installation weighing between 500 tons to 2100 tons at an average depth of 25 meters. 


Involves 10,000 meters of GRP DN4000 pipes installation between at 22 to 47  meters depths.